US nuclear reactors ran at a 91% capacity factor in 2025, higher than other types of power plants, but Georgia’s two newest reactors cost more than $30 billion to build. The US also holds about 99,000 metric tons of spent fuel and still has no permanent place to put it. The figures come mostly from EIA and DOE, along with GAO reports and a peer-reviewed land-use study, and they describe 2025 or 2026 unless a line says otherwise.
Top nuclear energy statistics
- Nuclear plants produced 785 billion kWh in 2025, which works out to 17.7% of US utility-scale electricity, a share calculated from EIA’s generation table.
- DOE says nuclear plants can employ up to 800 workers each and produce nearly half of the nation’s emissions-free electricity.
- The IPCC’s 2014 review put nuclear’s median lifecycle emissions at 12 grams of CO2 equivalent per kWh.
- Vogtle Units 3 and 4 were expected to cost $14 billion when construction began in 2009 and now cost more than double that.
- South Carolina’s V.C. Summer project was abandoned on July 31, 2017 after about $9 billion had been spent on two reactors that never ran.
- GAO counted about 86,000 metric tons of spent fuel at 75 US sites in 2021.
- DOE terminated its Yucca Mountain licensing effort in 2010 and Congress stopped funding the site.
- NRC says decommissioning a reactor generally costs $300 million to $400 million.
What are the pros and cons of nuclear energy?
Nuclear power’s strongest numbers are a 91% capacity factor in 2025 and low lifecycle emissions. Its weak spots are Vogtle’s cost overruns and a spent-fuel stockpile with no repository.
| Point | Pro or con | Number | Period and scope |
|---|---|---|---|
| Lifecycle emissions | Pro | 12 g CO2e per kWh, median | IPCC literature review, 2014 |
| Capacity factor | Pro | 91.1% | US utility-scale reactors, 2025 |
| Land use | Pro | 7.1 ha per TWh per year, median | Direct and indirect land, 2022 study |
| Clean electricity | Pro | Nearly half of emissions-free power | US, DOE |
| Jobs | Pro | Up to 800 workers per plant | US plants, DOE |
| Construction cost | Con | More than $30 billion against $14 billion planned | Vogtle 3 and 4, 2024 |
| Build time | Con | Service dates of 2023 and 2024 against targets of 2016 and 2017 | Vogtle 3 and 4 |
| Cancelled reactors | Con | About $9 billion spent | V.C. Summer 2 and 3, 2017 |
| Spent fuel | Con | About 99,000 metric tons, up about 2,200 a year | US commercial reactors, May 2026 |
| Waste disposal | Con | No repository, no Yucca funding since FY2010 | US, 2026 |
| Decommissioning | Con | $300 million to $400 million per reactor | NRC, generally |
| Accidents | Con | 28 of 134 Chernobyl workers with radiation sickness died within three months | Chernobyl, 1986 |
Source: IPCC, AR5 Annex III, EIA, Electric Power Monthly Table 6.07.B, PLOS ONE land-use study, DOE, Advantages and challenges of nuclear energy, EIA, Today in Energy, May 2024, CRS, Rising costs and delays doom new nuclear reactors in South Carolina, CRS, Nuclear Energy: Overview of Congressional Issues, NRC, Decommissioning fact sheet, UNSCEAR, Chernobyl.
The pros show up once a plant is running, and the cons sit at either end of its life, in the construction bill at the start and the waste and cleanup at the end. EIA counted 94 reactors in operation at 54 plants across 28 states in March 2026, and nuclear power’s future in the US starts from that fleet.
How much carbon does nuclear power produce?
The IPCC’s review put nuclear’s median lifecycle emissions at 12 grams of CO2 equivalent per kWh, with studies ranging from 3.7 to 110.
How reliable is nuclear power?
Nuclear plants ran at a 91.1% capacity factor in 2025, the highest in EIA’s table of non-fossil sources, against 33.8% for wind and 24.0% for solar PV. EIA reports average capacity factors by plant type, which compare a year’s output with the most the plants could have made.
| Source | Capacity factor, 2025 (%) | Utility-scale capacity (MW) |
|---|---|---|
| Nuclear | 91.1 | 98,408.2 |
| Geothermal | 65.9 | 2,681.2 |
| Wood | 55.8 | 7,289.1 |
| Hydroelectric | 34.4 | 79,984.0 |
| Wind | 33.8 | 155,344.4 |
| Solar photovoltaic | 24.0 | 134,526.3 |
Source: EIA, Electric Power Monthly, Table 6.07.B, 2025 annual figures.
How much of America’s clean electricity is nuclear?
About 42% of US carbon-free electricity in 2025 came from nuclear, a share calculated from EIA’s generation table, and DOE puts it at nearly half. The calculation adds nuclear, conventional hydro, solar and EIA’s category for other renewables, which includes biomass.
| Source | Generation, 2025 (GWh) | Share of carbon-free total (%) |
|---|---|---|
| Nuclear | 785,304 | 42.5 |
| Renewables excluding hydro and solar | 522,497 | 28.3 |
| Solar, utility-scale | 300,303 | 16.2 |
| Conventional hydro | 241,303 | 13.0 |
| Total | 1,849,407 | 100.0 |
Source: EIA, Electric Power Monthly, Table 1.1. Shares are calculated from EIA’s 2025 utility-scale figures.
How much land does nuclear power need?
Nuclear had the lowest median land use in a 2022 PLOS ONE study of real plants, 7.1 hectares per terawatt-hour a year, against 2,000 for ground-mounted solar PV.
| Source | Median land use (ha per TWh per year) | Observations |
|---|---|---|
| Nuclear | 7.1 | 59 |
| Wind, footprint basis | 130 | 57 |
| Natural gas, footprint basis | 410 | 17 |
| Hydroelectric, single-purpose dams | 650 | 952 |
| Coal | 1,000 | 30 |
| Natural gas, spacing basis | 1,900 | 4 |
| Ground-mounted solar PV | 2,000 | 94 |
| Wind, spacing basis | 12,000 | 57 |
Source: Lovering and colleagues, PLOS ONE, 2022, Table 1. Medians of direct and indirect land use, including fuel mining.

Wind and natural gas appear twice because the authors report them on two bases, and for wind the gap between the two is wide. The chart uses the footprint figures. The same authors found that adding the exclusion zones around Chernobyl and Fukushima raises nuclear’s figure by 3.9 hectares per TWh a year.
What did Vogtle 3 and 4 cost?
Georgia’s two new Vogtle reactors cost more than $30 billion against the $14 billion first expected. The Associated Press calculated the owners’ cost at $31 billion.
| Estimate | Date | Cost ($ billion) | What it covers |
|---|---|---|---|
| First estimate | 2009 | 14 | Units 3 and 4, all owners |
| Power Engineering report | November 2021 | 28.5 | Excludes $3.68 billion Westinghouse repaid |
| Georgia Power fact sheet | February 2023 | 10.2 | Georgia Power’s share only |
| EIA Today in Energy | August 2023 | More than 30 | Whole project |
| AP calculation | April 2024 | 31 | Owners’ cost, 35 with Westinghouse payments |
Source: EIA, Today in Energy, August 2023, Power Engineering, November 2021, Georgia Power, Vogtle 3 and 4 fact sheet, February 2023, Associated Press via Alabama Public Radio.
The figures differ because they count different things. Georgia Power’s $10.2 billion is its own share, and the others cover every owner, with or without the $3.68 billion Westinghouse repaid after its bankruptcy.
Unit 3 went commercial on July 31, 2023 and Unit 4 followed on April 29, 2024, against targets of 2016 and 2017. If you’re a Georgia Power customer, the AP reported that electric customers in Georgia already have paid billions for the plant.
SCE&G and Santee Cooper abandoned the V.C. Summer project on July 31, 2017 after spending about $9 billion when Westinghouse went bankrupt. In 2008 the owners planned Unit 2 for 2016 and Unit 3 for 2019, at $9.8 billion for both.
| Reactor | First in-service target | Outcome | Date |
|---|---|---|---|
| Vogtle Unit 3 | 2016 | Commercial operation | July 31, 2023 |
| Vogtle Unit 4 | 2017 | Commercial operation | April 29, 2024 |
| V.C. Summer Unit 2 | 2016 | Abandoned | July 31, 2017 |
| V.C. Summer Unit 3 | 2019 | Abandoned | July 31, 2017 |
Source: EIA, Today in Energy, May 2024, Southern Company, Vogtle Unit 4 release, CRS, Insight IN10750.
If you were an SCE&G customer, your bills had already carried about $1.4 billion for reactors that never produced power. Construction bills like these are one input into how nuclear and solar costs compare.
How much spent nuclear fuel does the US have?
The US held about 99,000 metric tons of commercial spent fuel in May 2026 and adds about 2,200 metric tons a year, CRS estimated.
| Date | Spent fuel (metric tons) | Source basis |
|---|---|---|
| December 2011 | More than 67,000 | CRS, metric tons |
| June 30, 2013 | 70,300.8 | EIA, tons of uranium |
| December 31, 2017 | 79,825.1 | EIA, tons of uranium |
| 2021 | About 86,000 | GAO, metric tons |
| May 2026 | About 99,000 | CRS, metric tons |
Source: CRS, Spent fuel storage, May 2012, EIA, Nuclear fuel data survey, GAO-21-603, CRS, Nuclear Energy: Overview of Congressional Issues.
US reactors loaded 44.4 million pounds of uranium oxide in 2022, and the uranium supply chain behind that fuel runs from mining through enrichment. DOE says the spent fuel is stored at more than 70 sites in 35 states, which may include yours, and that all of it would fit on a football field stacked less than 10 yards deep. DOE’s 2,000 metric tons a year runs a little below CRS’s estimate, and neither source gives its method.
The US has no permanent disposal facility for high-level waste. DOE applied for a Yucca Mountain license on June 3, 2008, and CRS reported in August 2026 that no new funding has been appropriated since FY2010 while it remains the sole authorized candidate site. Reprocessing is not permitted in the United States, though DOE says more than 90% of the fuel’s potential energy remains in it.
EIA says uranium is considered a nonrenewable energy source, which is the short answer to whether nuclear energy is renewable.
What does it cost to decommission a nuclear plant?
NRC says decommissioning generally costs $300 million to $400 million a reactor, and the work must finish within 60 years of shutdown. NRC lets owners cover that bill through a trust fund or a parent company guarantee, so the money is meant to be set aside before a reactor near you closes.
EIA says 19 reactors at 15 sites are in various stages of decommissioning, and those units sit outside the count of operating US nuclear power plants.
What is the nuclear accident record?
UNSCEAR reported that 134 of 600 workers at Chernobyl received high doses in 1986 and 28 of them died within three months. It also counted more than 6,000 thyroid cancer cases among children and adolescents exposed at the time, reported through 2005.
At Three Mile Island in 1979, NRC says small radioactive releases had no detectable health effects on workers or the public. Those two events anchor the argument over nuclear power’s safety record.
Where these numbers come from
We calculated nuclear’s carbon-free share from EIA’s utility-scale generation table and left small-scale solar out, so it won’t match DOE’s figure exactly. The Vogtle table shows each estimate with what it covers, and the spent-fuel table keeps each source’s units because EIA counts the uranium in the fuel and CRS and GAO count the whole fuel.
What Vogtle’s reactors will leave behind
Georgia Power says the new units will supply emissions-free energy for at least 60 to 80 years. DOE invited states on January 28, 2026 to host Nuclear Lifecycle Innovation Campuses that could include spent fuel storage and disposal sites.
Until one exists, DOE says the spent fuel can stay at reactor sites, and the fuel Vogtle makes will join the rest in pools and then dry casks beside the plant.