The average new wind turbine installed in the US in 2025 has a 141-meter rotor and a rating of 3.76 megawatts. Dongfang Electric says its 26-megawatt test turbine in China is the largest in the world, and it stands at a test base on land. The figures below come from Lawrence Berkeley National Laboratory, the US Department of Energy, IRENA and the wind trade press, and they describe 2025 unless a line says otherwise.

Top wind turbine statistics

How big is a new US wind turbine?

The average new US turbine had a 136.7-meter rotor and a 106-meter hub in 2024, and rotor diameter has grown in every period since 1998. The table gives the yearly averages for new land-based turbines.

Year installed Average rating (MW) Rotor diameter (m) Hub height (m)
1998 and 1999 0.716 48.2 56.6
2000 and 2001 0.888 52.9 58.2
2002 and 2003 1.234 63.6 66.2
2004 and 2005 1.456 73.6 74.1
2006 1.612 77.9 76.0
2007 1.646 79.0 78.2
2008 1.667 79.3 78.5
2009 1.742 81.5 78.8
2010 1.791 84.1 79.7
2011 1.966 89.0 81.0
2012 1.944 93.4 83.9
2013 1.865 96.9 80.5
2014 1.937 99.5 82.7
2015 2.003 102.4 82.4
2016 2.141 108.2 83.0
2017 2.320 113.0 86.0
2018 2.430 115.6 88.1
2019 2.551 121.2 90.1
2020 2.762 124.9 90.1
2021 2.994 127.4 93.9
2022 3.226 131.6 98.1
2023 3.400 133.8 102.0
2024 3.495 136.7 106.0
2025 (partial) 3.764 141.0 101.8

Source: Lawrence Berkeley National Laboratory, Land-Based Wind Energy Technology Data Update, 2026 edition. The 2025 row is partial: rating and rotor are known for 94% of installed projects and hub height for 75%, so it shouldn’t be compared with 2024.

Line chart of the average rotor diameter of new US land-based wind turbines, rising from 48 meters in 1998 and 1999 to 141 meters in 2025, and of hub height, rising from 57 meters to 106 meters in 2024
Chart: Energy Collective. Data: Lawrence Berkeley National Laboratory, 2026 edition.

Rotors kept growing. In 2024, 54.6% of new turbines had rotors of 130 meters or more, up from none in 2017.

What are the biggest wind turbines in the world?

The biggest turbine reported running in 2026 is Dongfang Electric’s 26-megawatt unit, which Dongfang says began sending power to the grid at a test base in Dongying, China, on October 29, 2025. It’s an offshore-class model on a land test site, and the rating is the company’s figure. Dongfang first rolled out the nacelle in October 2024, before any turbine stood.

Turbine Maker Rated power (MW) Rotor (m) Site Status
DEW-26 Dongfang Electric 26 310 Land test base Running, test unit
SG 21-276 DD Siemens Gamesa 21.5 276 Land test center Prototype
CTG-Goldwind 20 MW China Three Gorges, Goldwind 20 300 Offshore Running at sea
MySE18.X-20MW Mingyang 20 260 to 292 Land test site Test unit, blades broke
H260-18MW CSSC Haizhuang 18 260 Not stated Unveiled 2023
GWH252-16MW Goldwind 16 252 Offshore Installed at sea
V236-15.0 MW Vestas 15 236 Offshore Commercial
SI-270150 Sany 15 270 Onshore Installed
Twin-rotor floating Mingyang 50 (two 25 MW rotors) 290 each Floating offshore Announced

Source: offshoreWIND.biz on Dongfang, SASAC, POWER on Siemens Gamesa, offshoreWIND.biz on China Three Gorges, offshoreWIND.biz on Mingyang and New Atlas, POWER on CSSC Haizhuang, offshoreWIND.biz on the first offshore 16 MW turbine, Vestas, POWER on Sany, offshoreWIND.biz annual overview. Status as of September 2026.

Siemens Gamesa’s prototype and Dongfang’s unit stand on land test sites, and Mingyang’s test unit lost two blades in December 2024. CSSC Haizhuang unveiled its 18-megawatt design in January 2023.

Are offshore turbines bigger than onshore ones?

Yes. Europe’s new offshore turbines averaged 10.7 megawatts in 2025, against 5.2 onshore, roughly twice the size. The table lines up each average with the region and the year it covers.

Year Scope Turbine type Average rating (MW)
2022 Global Offshore 7.7
2023 Global Offshore 9.7
2024 Global Offshore 9.815
2024 Global Onshore Over 5
2025 Global Offshore 10.3
2025 Europe Onshore 5.2
2025 Europe Offshore 10.7
2025 Global All types 6.3

Source: US Department of Energy and NREL, Offshore Wind Market Report, 2024 edition, GWEC, 2024 supply-side data, GWEC, Global Offshore Wind Report 2026, WindEurope, 2025 statistics, GWEC, 2025 supply-side data. The DOE figures cover installations worldwide, and the 2025 all-types figure is GWEC’s installed capacity divided by its turbine count.

The 9.7-megawatt average for 2023 comes from the DOE and NREL offshore report and covers installations worldwide. WindEurope counts turbines that began sending power in Europe, while GWEC counts turbines installed worldwide, so the two averages aren’t directly comparable.

GWEC counted 28,395 new turbines and 178 gigawatts installed in 2025, which works out to about 6.3 megawatts per turbine.

Turbines going into US offshore projects are smaller than the Chinese models listed above, as the next table shows.

Project Turbine Rating (MW) Turbines
Vineyard Wind 1 GE Haliade-X 13 62
Revolution Wind Siemens Gamesa SG 11.0-200 DD 11 65
Coastal Virginia Offshore Wind Siemens Gamesa 14 176
Empire Wind 1 Vestas V236-15.0 MW 15 54

Source: Vineyard Wind, offshoreWIND.biz on Revolution Wind, offshoreWIND.biz on Coastal Virginia Offshore Wind, Empire Wind.

If you live on the coast between Massachusetts and Virginia, these are the machines going into the water off your shore. Coastal Virginia’s first turbine went up in January 2026, and the project was 81% complete on July 31, 2026.

How long can wind turbine blades get?

The longest blade reported is 153 meters long, on Dongfang’s 26-megawatt test unit.

Blade length (m) Turbine Type Year
153 Dongfang 26 MW Land test unit 2025
147 China Three Gorges and Goldwind 20 MW Offshore 2026
131 Sany 15 MW Onshore 2024
115.5 Vestas V236-15.0 MW Offshore Introduced 2021
107 GE Haliade-X 12 MW Offshore prototype 2019

Source: offshoreWIND.biz annual overview, offshoreWIND.biz on China Three Gorges, POWER on Sany, Vestas, Port of Rotterdam.

Why do bigger rotors pay off?

Bigger rotors pay off because they catch more wind for each kilowatt of generator, and Lawrence Berkeley National Laboratory says a lower rating per rotor area should raise capacity factor. That’s the share of its maximum output a turbine delivers over a year. A longer blade sweeps a wider circle of air, so the same generator sees more wind.

Engineers call that rating per rotor area specific power. It fell from 393 to 237 watts per square meter on new US turbines installed from 1998 and 1999 through 2023.

If a wind farm has gone up near you since 2023, its turbines most likely have big rotors, since DOE found that 98% of new turbines in 2023 had rotors 115 meters or wider. The page on wind turbine efficiency covers what that does to a turbine’s output.

How much does wind power cost?

Bigger turbines lower the cost of a wind farm because fewer turbines are needed to generate the same energy, DOE says.

IRENA reports 2025 costs of $33 per megawatt-hour for onshore wind and $78 for offshore, and says cheaper equipment and installed costs were offset by a higher cost of capital and slightly lower capacity factors. IRENA doesn’t separate out the effect of turbine size.

Wind power cost, 2025 Cost ($ per MWh, 2025 dollars)
Global onshore 33
Global offshore 78
China onshore 27
China offshore 49
US offshore 141

Source: IRENA, Renewable Power Generation Costs in 2025, executive summary.

How did wind turbines get from 12 kilowatts to 26 megawatts?

Charles Brush built a 12-kilowatt wind turbine in Cleveland in the 1880s, and Case Western Reserve University dates it to 1888. The table follows the story from there to Dongfang’s test unit.

Year Turbine Rated power (kW)
1888 Brush turbine, Cleveland 12
1941 Smith-Putnam, Vermont 1,250
1957 to 1967 Gedser, Denmark 200
1975 NASA Mod-0, Ohio 100
1987 to 1996 Boeing Mod-5B, Hawaii 3,200
2004 REpower 5M prototype, Germany 5,000
2019 GE Haliade-X prototype, Rotterdam 12,000
2023 Goldwind GWH252-16MW, offshore China 16,000
2025 Dongfang DEW-26, land test base 26,000

Source: US Department of Energy, Case Western Reserve University, IEEE Engineering and Technology History Wiki, NASA, OSTI, Renewable Energy World, offshoreWIND.biz on the Haliade-X, offshoreWIND.biz on the first offshore 16 MW turbine, SASAC.

The Smith-Putnam turbine ran for 1,100 hours before a blade failed. Sources disagree on its size, since IEEE’s history wiki titles its page on the machine 1.5 megawatts and the table uses DOE’s 1,250 kilowatts. NASA switched on Mod-0 on October 29, 1975.

Why can’t onshore turbines just keep growing?

Roads set the limit. NREL’s 2014 transportation study found US roads generally cap a single-piece blade at 53 to 62 meters, and DOE says blades can’t be folded or bent once they’re built. Tower sections are generally limited to 4.3 meters wide, so they fit under overpasses.

If you’ve been stuck behind a truck hauling one blade around a highway curve, that’s the limit at work. By rail, NREL puts the ceiling for a single-piece blade at 75 meters.

Those limits describe US roads and rails, and they don’t bind everywhere. Sany installed a 15-megawatt onshore turbine with a 131-meter blade in Jilin, China, in October 2024.

How big are home wind turbines?

A small turbine that can power one home has a capacity of about 10 kilowatts, and DOE defines small turbines as anything from 20 watts to 100 kilowatts.

Small wind in the US, 2024 Value
Turbines sold 160
Capacity installed (MW) 2.0
Investment ($ million) 13.5
Average installed cost ($ per kW) 6,680
Average capacity factor, small turbines (%) 16

Source: Pacific Northwest National Laboratory, Distributed Wind Energy Technology Data Update, 2025 edition.

If you’re pricing a home turbine, $6,680 per kilowatt means a home-size system would cost about $66,800 installed, and that average rests on a small sample. Small turbines in PNNL’s 2024 sample ran at a 16% capacity factor, well below the 24% for midsize and large ones.

Where these numbers come from

Two figures are computed from the sources above. The 2025 world average turbine size is GWEC’s installed capacity divided by its turbine count, and the installed cost of a home-size system is PNNL’s cost per kilowatt scaled up to a home-size unit. The 2025 US figures are partial, so hub height isn’t compared between 2024 and 2025 and the chart leaves that point blank. GWEC counts turbines installed and WindEurope counts turbines that began sending power, so their averages differ by design.

Where Coastal Virginia and Empire Wind stand

The last of Coastal Virginia’s 176 turbines is expected to go up by the end of 2027. Empire Wind 1’s plan calls for 54 Vestas turbines rated at 15 megawatts each, for New York.

For what these projects cost and where they stand, see the page on offshore wind power. For how much wind the US has built so far, see wind power in the US.